Notice to Residents: Ongoing PSEG Construction in Merchantville Featured

Rate this item
(0 votes)

PSEG is beginning the restoration and paving work related to the electric transmission upgrades in Merchantville. Restoration work on Lexington Avenue between West Maple and North Chestnut will begin this week. Paving and restoration on Lexington Avenue between W. Maple and Wisteria Avenue has started in Pennsauken and will work its way north to Merchantville. They are scheduled to complete all paving by the second week of December.