Thursday, 13 November 2014 00:00
Notice to Residents: Ongoing PSEG Construction in Merchantville Featured
PSEG is beginning the restoration and paving work related to the electric transmission upgrades in Merchantville. Restoration work on Lexington Avenue between West Maple and North Chestnut will begin this week. Paving and restoration on Lexington Avenue between W. Maple and Wisteria Avenue has started in Pennsauken and will work its way north to Merchantville. They are scheduled to complete all paving by the second week of December.
Published in
Notices
Leave a comment
Make sure you enter all the required information, indicated by an asterisk (*). HTML code is not allowed.